Upper saloon – the inside is taking shape…

Pano of Upper Saloon

A new suspended floor is being installed that allows for services & ventilation to be connected underneath. The portholes are going in this week, with the larger windows being glazed in a few weeks time. Next will be the doors and then it will be water tight.

It’s a huge space that we will be able to enjoy with some amazing views. Our aim is to have it in service by the start of next season.

Light tower renovation begins

The light tower has been scaffolded to allow for its renovations and re-painting. Areas are being repaired, redundant fittings removed and glazing bars fitted; before a new coat of paint is applied.

The light tower is the reason the ship was built and is the central feature of the new design – it’s going to look amazing!